Fifteen year-old block and brick building in need of major internal and external renovation according to architects
Yavapai Community College Vice President Clint Ewell unveiled the cost estimates the Community College is anticipating paying for renovating the inside of building “L,” building a shroud of some sort around it, and improving utilities leading to the facility. According to the college, the total may run to almost $7 million. This was almost double the previous estimates made by the Community College.
Here is a breakdown of the anticipated costs for renovating Building “L” the Community College gave the Governing Board at its March 5 meeting:
Direct cost of connecting to central plant/fan coils: (work not completed in 2011-13) $430,000
Cost of FCA items – LED lighting, signage, Lauren, sprinklers: $530,000
Construction including renovation and equipment: $5,341,790
Additional funding in following year: $672,210
Total: $6,974,000
A short video clip with Dr. Ewell proving a summary of the costs appears below.